Building & Infrastructure

Projects & Public Works

Road projects in Oak Bay cover a wide range of work, from physical buildings to roads and sewers. The range in scale from large infrastructure projects that take weeks or months, to smaller scale projects that take days. Find details on upcoming projects in the two tables below.

Capital Projects

Public Works and Maintenance

StartEnd (anticipated)LocationWork being doneTraffic Impacts
7/2/20257/3/2025Foul Bay Rd. at HaultainWork being done for the Florence Street Infrastructure project.Single lane alternating traffic
7/2/20257/4/2025Cadboro Bay Road - Between Lansdowne and DufferinSewer and Water service installation.Single lane alternating traffic

Water Main Flushing

Water main flushing cleans water distribution pipes and reservoirs of sediments that build up over time. Water main flushing provides the following system benefits:

  • Improved water quality.
  • Improved system hydraulic capacity.
  • Improved system operation by identifying weak or problem areas.
  • Improved/restored chlorine residual.
  • Increased life of system components; including, pressure reducing valves, line valves, pumps, etc.

How does flushing affect me?

During the flushing process, you may experience low pressure and discoloured water. Any discolouration is temporary and is not a health hazard. If you experience discoloured water, please run the cold water tap in your bathtub or laundry tub to avoid clogging screens in faucets.

If you have any questions, contact Public Works at 250-598-4501