Road projects in Oak Bay cover a wide range of work, from physical buildings to roads and sewers. The range in scale from large infrastructure projects that take weeks or months, to smaller scale projects that take days. Find details on upcoming projects in the two tables below.
Capital Projects
Project | Start | End (anticipated) | Work being done | Location | Follow |
---|---|---|---|---|---|
Florence Street Infrastructure | 12/2024 | Early Summer 2025 |
| Florence Street: Haultain to Cadboro Bay Road. Jacks Lane | Details |
Uplands Sewer Separation (phase one) |
| Humber Catchment (phase one) | Details | ||
Estevan Utilities Project | 3/2025 |
| Estevan Ave: Willows Beach to Heron St. Lincoln Rd: Estevan to Burdick Ave. | Details |
Public Works and Maintenance
Start | End (anticipated) | Location | Work being done | Traffic Impacts |
---|---|---|---|---|
5/6/2025 | 5/6/2025 | 2095 Oak Bay Ave | Crews performing water meter upgrade. Traffic will be maintained both directions, however please obey cones and crew in the construction zone. |
Water Main Flushing
Water main flushing cleans water distribution pipes and reservoirs of sediments that build up over time. Water main flushing provides the following system benefits:
- Improved water quality.
- Improved system hydraulic capacity.
- Improved system operation by identifying weak or problem areas.
- Improved/restored chlorine residual.
- Increased life of system components; including, pressure reducing valves, line valves, pumps, etc.
How does flushing affect me?
During the flushing process, you may experience low pressure and discoloured water. Any discolouration is temporary and is not a health hazard. If you experience discoloured water, please run the cold water tap in your bathtub or laundry tub to avoid clogging screens in faucets.
If you have any questions, contact Public Works at 250-598-4501