Building & Infrastructure

McNeill Avenue Capital Works

About the Project

Location: McNeill Avenue – Transit to Foul Bay Rd.
Type of Work:  Underground utilities and pedestrian and cycling infrastructure
Stage: Bid for Contractor
Construction Timeline: August 2025 – Summer 2026

We’re undertaking critical infrastructure improvements along McNeill Avenue including upgrades to underground utilities, improvements to roadways, pedestrian and cyclist safety. The work will include:

If you have any questions regarding this project, please contact engineering@oakbay.ca. For project and engagement history, visit our Connect Oak Bay page

Water Main

1,270 metres

Sanitary Sewer

124 metres

Storm Main

127 metres

Project Updates

On Monday, July 28, Oak Bay Council awarded the contract for the McNeill Utility Replacement and Traffic Calming Project to C-1 Contractors Ltd.

Staff will now work with C-1 Contractors leading up to the anticipated beginning of construction in late-August.

Detailed design is complete and the construction phase of this project is anticipated to begin in August 2025, following contractor procurement through a competitive bidding process. The Invitation to Tender has been posted to BC Bid and the project is scheduled to be awarded in July.

Completion of this project is anticipated for Summer 2026, depending on the contractor’s work schedule.

Traffic Impacts