About the Project
Location: Topp Avenue
Type of Work: Replacement of underground utilities (watermain and storm main), new curb installation, and surface restoration including road paving.
Stage: Construction
Construction Timeline: Anticipated completion in September 2025
This renewal project supports long-term infrastructure resilience and enhances the overall condition and function of Topp Avenue. The project includes:
- Replacement of the storm drainage system
- Upgraded watermain
- Installation of new concrete curb
- Complete road regrading and paving
- Boulevard restoration
If you have any questions regarding this project, please contact engineering@oakbay.ca.
Water Main
Approximately 160 meters
Concrete Curb
Approximately 276 meters
Storm Main
141 meters
Project Updates
September 19-22 | Road Grading and Paving
Road grading and paving are planned for Topp Ave. as part of this utility replacement project. Residents will be delivered notifications and can expect delays on the following days:
Friday Sept. 19 | Final Road Grading: Crews will be on-site for the final grading of the roadway. Local access will be accommodated but expect minor delays.
Mon. Sept 22 | Paving: Crews will complete full-width paving of Topp Ave. (weather dependent). During this work, from 7:00 a.m. to 5:00 p.m., the road will be closed to all vehicle traffic with no on-street parking.
August 2025 | Remaining Work
The remaining work for this project includes:
Mid-August: Curb installation and full asphalt removal and casting adjustments.
Late August: Road grading
September: Paving (weather permitting) and irrigation repair and boulevard reinstatement. Surface work is expected to be complete by mid-September.
*Please note these anticipated timelines and subject to change.