Oak Bay Ave. at Wilmot Pl. Crosswalk

About the Project

Location: Crosswalk at Oak Bay Ave. at Wilmot Pl.
Type of Work:  Intersection improvements
Construction Timeline: October – Early 2026

The District of Oak Bay is undertaking improvements at the intersection of Oak Bay Avenue at Wilmot Place to enhance pedestrian safety and accessibility in the heart of our community.

These upgrades will shorten pedestrian crossing distances, improve sightlines, calm vehicle traffic and create a safer, more accessible intersection for all users.

Timeline and Questions

Work will be carried out by District staff. If you have any questions regarding this project, please contact engineering@oakbay.ca. 

Project Updates

Crews are scheduled to start work on the north side of the crosswalk on Monday, March 16. This work in anticipated to take two to three weeks and will see:

  • Construction of a concrete curb extension
  • Installation of pedestrian activated crossing lights
  • Restoration of paving to ensure a smooth transition between new and existing asphalt
  • Crosswalk line painting and markings.

Traffic Impacts

There will also be periods of single lane alternating traffic on Oak Bay Ave., when required. Crews plan to work Monday through Friday, between 7:00 a.m. and 3:00 p.m. Temporary parking restrictions will be in effect during work hours near the work zone.

During construction, access to Wilmot Place will be through Theatre Lane off Hampshire. Traffic leaving Wilmot will be one-way onto Oak Bay Ave.

Oak Bay Engineering and Public Works will be planning work on the north end of this crosswalk for early 2026, to avoid impacts to businesses and pedestrians during the busy holiday season.

The finishing touches on the south side (Fairway Market) curb extension are planned for this week.

  • Tuesday, October 28: Crews will be installing concrete sidewalk for the bump out
  • Wednesday, October 29: Installation of the remainder of the sidewalk

Work on the south end is anticipated to be complete this week, with work scheduled on the north side scheduled for early 2026.

District of Oak Bay Public Works crew will begin work on Monday, October 6. Traffic impacts will be minimal, with possible lane adjustments but two-way traffic maintained.

Cyclist and bus access will be maintained throughout the project. Traffic control personnel will be on-site to assist pedestrians.