Uplands Road Water Main Construction

The District will be replacing a 200 mm water main along Uplands Road between Cardigan Road and Upper Terrace Road.  The aim of the project is to replace an aging water main in order to improve the integrity of the water supply system to continue providing residents with reliable fire-fighting flows and clean drinking water.  The project will commence during the week of August 10, 2020, and will be completed by November 2020.  Disruptions to water service are anticipated, but will be minimized or avoided as much as possible.  Public Works will provide 24-hours notice before any scheduled shut-off.  Parking along these sections of road will be disrupted due to the construction activities.

July 23, 2020 - Construction Notice to residents issued.

September 8, 2020 - Construction continues on schedule and on budget.